Ocean Pines Wireless Tower Proposal

Updates: Town Hall Scheduled

About the Project

In an ongoing effort to provide quality wireless service, T-Mobile, Verizon and AT&T have identified your community as one that will benefit from improved network coverage. 

Milestone Towers is proposing a wireless telecommunications facility at the Ocean Pines GolfMaintenance Area.

Address: 100 Clubhouse Dr, Ocean Pines, MD 21811

The proposal is for a 150-foot monopole and will include ground equipment required to operate the facility. 

This equipment will be located at the base of the structure in a secure fenced area.

Our Process

1. Due Diligence 

Survey, FAA, FCC, NEPA, Phase 1, Geotechnical Analysis.

2. Land Use

Special Use Permit Application, Community Meeting, Staff Review, Planning Commission, Board of Supervisors.

3. Permitting

Conduct Bid Walk With Contractors and school representatives, submit permit application, 60 Day Review Period

4. Construction 

Tower construction = 4-6 weeks  | Carrier construction = 4-6 weeks on average

 

5. Site Maintenance

Four visits per year for site maintenance | Remove trash, debris, check signage. 